Project details
Project location:
Stockton, California
Project Type:
Design / Build
year completed
2013
DESCRIPTION:
Utilizing the design/build project delivery method New England Sheet Metal and Mechanical Co. (NESM) self-performed all work related to the site utilities, excavation & grading, structural & site concrete, process piping, mechanical, plumbing and all equipment installation. Among other components, the 80’ tall (7-story) structural steel tower supports an 11’ diameter by 60’ tall vessel that is instrumental to the plant processes. The project team spent several months in preconstruction in order to properly plan the work and efficiently execute over 100,000 craft hours of work. This project was also awarded the Golden Gate Partnership Recognition by Cal/OSHA for demonstrating commitment to workplace safety and health.